What are you pouring?
Strength
Slabs, most house work. Area = length × width.
Concrete
2.16
m³ incl. 8%
Cement
16
bags, 50 kg
Stone
1.5
m³, 19 mm
Before waste
2 m³
Concrete sand
1.5 m³ (needs 1.4)
Stone, 19 mm
1.5 m³ (needs 1.4)
Sign in to save to a project

Free. Your numbers come with you.

How it’s worked out

  1. Volume = 20 m² × 0.1 m = 2 m³
  2. With waste = 2 × 1.08 = 2.16 m³
  3. Cement = 2.16 × 7 bags = 15.1, rounded up to 16 bags
  4. Sand = 2.16 × 0.65 = 1.4 m³, ordered as 1.5 m³
  5. Stone = 2.16 × 0.65 = 1.4 m³, ordered as 1.5 m³

Assumptions

  • A 25 MPa site mix, per m³ of concrete: 7 bags of cement, 0.65 m³ concrete sand, 0.65 m³ of 19 mm stone.
  • Sand and stone are loose volumes, the way suppliers sell them, ordered in half cubes (0.5 m³).
  • Cement is in 50 kg bags.

Waste allowance

  • 8% on the concrete, for spill, an uneven base and over-dig.

Ask your engineer to confirm

  • The strength (MPa) for each part of the job is the engineer’s call, not this calculator’s.
  • Above about 3 m³ in one go, ask for a ready-mix price as well.