Tools
Sign inServitude clearance
Walls
0.57
m clear
Footings
0.38
m clear
Building line
0.57
m clear
- Corner A · 2.57 m
- walls 0.57 · footings 0.38Pass
- Corner B · 2.57 m
- walls 0.57 · footings 0.38Pass
Sign in to save to a project
Free. Your numbers come with you.
How it’s worked out
- Corner A, walls = 2.57 − 2 = 0.57 m
- Corner A, footings = 2.57 − 0.19 − 2 = 0.38 m
- Corner A, building line = 2.57 − 2 = 0.57 m
- Corner B, walls = 2.57 − 2 = 0.57 m
- Corner B, footings = 2.57 − 0.19 − 2 = 0.38 m
- Corner B, building line = 2.57 − 2 = 0.57 m
Assumptions
- Positive is clear of the line, negative is inside it.
- Clear means 10 mm or more to spare. Less than that is “check”: it’s within setting-out error, so have a land surveyor peg the corners.
- Walls are checked against the servitude and the building line. Footings are wider than the wall, so they’re checked against the servitude on their own.
- Roof overhangs, steps and paving aren’t checked here.
Waste allowance
- None: these are distances, not quantities.
Ask your engineer to confirm
- Nothing may be built inside a servitude, footings included, without the written consent of whoever holds it (the municipality, for a sewer).
- Footings near a sewer pipe may need to go deeper than the pipe. The engineer decides.
- Building over a building line needs a relaxation from the council, usually with the neighbour’s consent.