Tools
Sign inFoundation take-off
Stand 5540 exampleConcrete
6.05
m³ incl. 8%
Concrete mix
8
m³ sand + stone
Cement
43
bags, concrete
- Footings
- 3.27 m³
- Slab
- 2.33 m³
- Ref 193 mesh, 2.4 × 6 m
- 3 sheets
Sign in to save to a project
Free. Your numbers come with you.
How it’s worked out
- Footings = 23.7 m × 0.6 m × 0.23 m = 3.27 m³
- Slab = 27.45 m² × 0.085 m = 2.33 m³
- Concrete = (3.27 + 2.33) × 1.08 = 6.05 m³
- Concrete mix = 6.05 × 1.3 = 7.87, rounded up to 8 m³
- Cement = 6.05 × 7 bags = 42.4, rounded up to 43 bags
- Mesh = 27.45 m² × 1.15 ÷ 14.4 m² a sheet = 2.19, rounded up to 3
Assumptions
- Strip footings under every wall, plus one ground slab. Sizes in metres in the working.
- 7 bags of 50 kg cement per m³ of concrete, about a 25 MPa site mix.
- 1.3 m³ of concrete mix (sand and stone, loose) per m³ of concrete.
- Ref 193 mesh (welded steel mesh for the slab) comes in 2.4 × 6 m sheets, 14.4 m² each.
Waste allowance
- 8% on concrete for over-dig, uneven trenches and spill. 15% on mesh, where sheets overlap.
Ask your engineer to confirm
- Footing width and depth: the engineer sets these to suit your soil (SANS 10400-H).
- Concrete strength and the mesh, and how much concrete cover the mesh needs.
- Whether the slab must be thickened under internal walls.